|
UTILITY COMPANY St. Louis, Missouri
The objective of this project for Remedial Construction Services, L.P. (RECON) was to stabilize a 700-foot stretch of a creek bank that ran along the backside of the client's property.
Initially, the project included the removal of existing trees and vegetation to allow access to the creek. RECON then excavated the existing fill materials, removed undesirable fill materials, and regraded and compacted the new materials to the required lines and grades. Approximately 1,500 feet of maintenace road was installed, including a french drain system in the lower portion of the access road.
Final grading of the upper slope included placement of vegetation with erosion control matting, popular trees, and grass seed. The lower slopes received a layer of geotextile, followed by a layer of Geoweb, which was filled with silty clay and AquaBlok (TM) material. The Geoweb was covered by a layer of Stratapec along with a layer of crushed limestone and riprap.
In order to the anchor trench in the creek bottom to be installed correctly, the creek was temporarily diverted using submersible pumps powered by a mobile generator unit.
Re-vegetating the remaining disturbed areas and installing approximately 900 feet of six-foot tall chain-link fencing completed the project.
|